Message Title
Dear all,
I have a new error now when importing event through csv file: “Process failed: Event needs to have completed date. “
What is this “completed date”? Is this new in 2.27?
Best
Lise
···
From: Viet Nguyen (JIRA) [mailto:issues@dhis2.org]
Sent: 11 July 2017 11:23
To: GROUT, Lise
Subject: [dhis2-issue] (DHIS2-1905) Error when importing events through csv file and Import/Export App
Viet Nguyen commented on DHIS2-1905
Re: Error when importing events through csv file and Import/Export App
I have applied a fix for this issue, let me know if it works for you, then I will close the ticket.
This message was sent by Atlassian JIRA (v7.2.3#72005-sha1:73be91d)