Hi all, i would like a clarification on this:

The previous versions before 2.13, we used to set Days after period end to qualify for timely data submission =5 and the system counts 5 days after the end of month, and any report after 5 days is not timely reported.

But now we set out datasets as Days after period end to qualify for timely data submission = 5, the system picks only 4 days and any report on 5th day the system takes it as late reporting…

Any clarification on this? our time reporting is 5 days after each month, do we have to put 6? to have 5days?

This is something related to >5, This is better >=5

Regards!

···